Contract No: 8365/2021 - Lot 2
28/02/2024
28/05/2025
Executive Project, Supply of materials and Construction of the Transmission Line LT-220 kV SRI-MAU. The María Auxiliadora and Santa Rita Substations can be interconnected through this project, the length of the Line is 89 km and will have a double ACAR conductor of 950 MCM per phase.
National Electricity Administration (A.N.D.E.)